Mostrar el registro sencillo del ítem
Análisis de obras ejecutadas bajo la modalidad de administración directa, Periodo 2019-2022. de la municipalidad distrital Cajaruro, provincia Utcubamba, departamento Amazonas
| dc.contributor.advisor | Blas Rebaza, Rocío del Pilar | es_PE |
| dc.contributor.author | Yomona Morales, John Roberth | es_PE |
| dc.date.accessioned | 2026-09-30T14:47:44Z | |
| dc.date.available | 2026-09-30T14:47:44Z | |
| dc.date.issued | 2026-08-31 | |
| dc.identifier.uri | https://hdl.handle.net/20.500.12893/17802 | |
| dc.description.abstract | El presente estudio tuvo como finalidad analizar las obras ejecutadas bajo el sistema de administración directa durante el periodo 2019–2022 por la Municipalidad Distrital de Cajaruro, provincia de Utcubamba, departamento Amazonas. La investigación se desarrolló con objetivo de evaluar el desempeño de los proyectos públicos respecto al cumplimiento presupuestal, los plazos de ejecución y el cumplimiento técnico. Metodológicamente, la investigación presentó un diseño no experimental de corte transversal, nivel descriptivo, enfoque cuantitativo, de tipo aplicada. La muestra fue constituida por diez proyectos ejecutados bajo la gestión directa del municipio. La técnica empleada fue el análisis de documentos, mediante la revisión de expedientes técnicos, valorizaciones, cronogramas, informes y registros presupuestales. Los resultados evidenciaron que varias obras presentaron subejecución financiera y diferencias entre el presupuesto programado y el ejecutado. Asimismo, algunas obras incumplieron los plazos establecidos, registrándose retrasos en la ejecución física. En el aspecto técnico, la mayoría de proyectos contó con aprobación de trabajos y conformidad de valorizaciones, aunque algunas obras evidenciaron cumplimiento parcial del expediente técnico y del control de calidad. Se concluye que los proyectos ejecutados bajo administración directa presentaron resultados diferenciados en eficiencia presupuestal, cumplimiento de plazos y cumplimiento técnico, evidenciándose la necesidad de fortalecer el planeamiento, supervisión y control técnico-administrativo para maximizar futuras ejecuciones de obras del estado. | es_PE |
| dc.description.abstract | This study aimed to analyze the public works projects executed under the direct administration system during the period 2019–2022 by the District Municipality of Cajaruro, Utcubamba Province, Amazonas Department. The research was conducted to evaluate the performance of these projects with respect to budget compliance, execution deadlines, and technical compliance. Methodologically, the research employed a non- experimental, cross-sectional, descriptive, quantitative, and applied design. The sample consisted of ten projects executed under the municipality's direct management. The technique used was document analysis, through the review of technical files, valuations, schedules, reports, and budget records. The results showed that several projects exhibited financial under-execution and discrepancies between the planned and executed budgets. Furthermore, some projects failed to meet established deadlines, resulting in delays in physical execution. From a technical standpoint, most projects received work approval and valuation confirmations, although some projects showed partial compliance with the technical specifications and quality control requirements. It is concluded that projects executed under direct administration showed varying results in terms of budget efficiency, adherence to deadlines, and technical compliance, highlighting the need to strengthen planning, supervision, and technical-administrative control to maximize future execution of state works. | es_PE |
| dc.format | application/pdf | es_PE |
| dc.language.iso | spa | es_PE |
| dc.publisher | Universidad Nacional Pedro Ruíz Gallo. | es_PE |
| dc.rights | info:eu-repo/semantics/openAccess | es_PE |
| dc.rights.uri | http://creativecommons.org/licenses/by-nc-nd/4.0/ | es_PE |
| dc.subject | Obras públicas | es_PE |
| dc.subject | Administración directa | es_PE |
| dc.subject | Ejecución presupuestal | es_PE |
| dc.subject | Cumplimiento de plazos | es_PE |
| dc.subject | Cumplimiento técnico | es_PE |
| dc.title | Análisis de obras ejecutadas bajo la modalidad de administración directa, Periodo 2019-2022. de la municipalidad distrital Cajaruro, provincia Utcubamba, departamento Amazonas | es_PE |
| dc.type | info:eu-repo/semantics/masterThesis | es_PE |
| thesis.degree.name | Maestro en Gerencia de Obras y Construcción | es_PE |
| thesis.degree.grantor | Escuela de Postgrado | es_PE |
| thesis.degree.discipline | Maestría en Gerencia de Obras y Construcción | es_PE |
| dc.type.version | info:eu-repo/semantics/submittedVersion | es_PE |
| dc.publisher.country | PE | es_PE |
| dc.subject.ocde | http://purl.org/pe-repo/ocde/ford#2.01.03 | es_PE |
| renati.author.dni | 45488103 | |
| renati.advisor.dni | 18080838 | |
| renati.advisor.orcid | https://orcid.org/0000-0002-9376-3095 | es_PE |
| renati.type | http://purl.org/pe-repo/renati/type#tesis | es_PE |
| renati.level | http://purl.org/pe-repo/renati/nivel#maestro | es_PE |
| renati.discipline | 732027 | es_PE |
| renati.juror | Mondragón Castañeda, Carlos Ernesto | es_PE |
| renati.juror | Dávila Vidarte, Domingo Jorge Luis | es_PE |
| renati.juror | Huangal Castañeda, Nelson Enrique | es_PE |